11/18/14 7:05pm
11/18/2014 7:05 PM

liveblog

The tentative 2015 Riverhead Town Budget proposed by Supervisor Sean Walter at the end of September will apparently became the adopted 2015 budget automatically on Thursday, Nov. 20, as a motion to vote on adopting the budget failed at Tuesday’s Town Board meeting.

Councilman John Dunleavy, who said he opposes the budget because he thinks the revenue projections it makes are unrealistic,  submitted a resolution Tuesday to merely vote on adopting the budget. Councilwoman Jodi Giglio, who had sought cuts in the budget, voted in favor of voting on the budget as well. However, Councilmen George Gabrielsen and Jim Wooten voted against the resolution, saying it doesn’t propose any changes to the budget, and the budget will go into effect automatically if no changes are approved. Mr. Walter abstained.

Mr. Walter’s $53.7 million proposed budget called for a 1.5 percent spending decrease, a .58 percent tax rate increase and a 2.08 percent tax levy increase. There were no speakers at the public hearing on the budget two weeks ago.

The  Town Board also voted Tuesday to accept a proposed settlement with Brixmor Property Group, which owns the Costco shopping center on Route 58. Brixmor has thus far failed to meet several requirements of its site plan approval, including replacing dead trees meant as a buffer for neighboring properties.  (more…)

06/27/14 3:00pm
06/27/2014 3:00 PM
The Costco Wholesale store was packed Thursday, its opening day. (Credit: Tim Gannon)

The Costco Wholesale store was packed Thursday, its opening day. (Credit: Tim Gannon)

Despite a number of controversies over the past year, the Riverhead Costco store was issued a temporary certificate of occupancy in time to meet its announced June 26 opening date  on Thursday.

And it was greeted by large crowds of shoppers. Costco

“We are thrilled to be bringing Costco’s low warehouse prices to the residents of Riverhead,” warehouse manager Jon Jovel said in a press release. “They have been asking us to open here for a long time, and we already have made an impact on the local job market. We look forward to contributing to the community in many ways.”

Town officials had previously said the store would not be issued a CO, allowing it to open to the public, unless it met all of the conditions of a May 15 amended site plan approval issued by the town Planning Board.

The approval required the developer of the site, Brixmor Property Group, to  replace a wooden fence around the property with a chain link fence with privacy slats, and to plant all of the trees buffering neighboring properties that had been previously called for in the earlier approval — and, lastly, to replace trees that have since died.

It also required them to spread out excess sand on the property over a 20-acre portion of the site, resulting in the grade of the land being raised by 3.5 feet over the prior Planning Board approval from the fall of 2012.

Residents in the Foxwood Village development to the north and the Millbrook Community development to the east had complained about the lack of screening between their homes and the shopping center after Brixmor, with Town Board and Planning Board approvals, clearcut the entire 41 acre site, even though the builders only planned to develop a portion of it.

According to Riverhead Supervisor Sean Walter, the store was issued a temporary CO and not a permanent one because the traffic light, which it shares with another shopping center across the street, had not been fully accepted by the Suffolk County Department of Public Works, and because the developer needed to sprinklers and hydroseed — a type of fast growing grass — on a 20-foot section of lawn around the parking lot.

Mr. Walter said both were being done, and he doesn’t anticipate the store will have any problems getting the permanent CO.

He said all the other requirements of the amended site plan approval have been met.

The Costco site is actually separately owned from the rest of the shopping center, which is called The Shops at Riverhead and is owned by Brixmor. However, another part of the amended site plan allowed the developers to build just the Costco store initially, since they didn’t have any tenants yet for the rest of the project.

Robert Hall, a Foxwood Village resident who has represented the homeowners there at planning meetings on the development for several years, was not happy that the town granted the CO.

“They said that unless they completed everything on the amended site plan, they wouldn’t get a CO,” he said. “I don’t believe they’ve completed everything.”

Although new spruce trees were planted along the border with the Foxwood and Millbrook communities, he said the builders never removed the arborvitae trees that were previously planted. He said he and many other residents agree the trees “look like junk.”

tgannon@timesreview.com

Caption: Neighbors have complained about these arborvitae shrubs. (Credit: Tim Gannon, file)

05/01/14 10:26pm
05/01/2014 10:26 PM
CAPTION: Haig Buchakjian, center, the Senior Vice President of Construction with Brixmor Property Group, promised to make things better at the Costco/Shops at Riverhead development at Thursday's Riverhead Planning Board meeting, while some of the neighbors who have been angered by that development look over his shoulder.

Haig Buchakjian of Brixmor Property Group, center, promising to improve current construction plans at the Costco shopping center during Thursday’s Riverhead Planning Board meeting while residents — who’ve been angered by ongoing construction issues at the site — look over his shoulder. (Credit: Tim Gannon)

With angry neighbors literally looking over his shoulder, the senior vice president of construction with Brixmor Property Group told the Riverhead Planning Board Thursday night that things will improve at the controversial Costco/Shops at Riverhead development, which has run into complaints from neighbors and town officials and was put under a stop work order last Friday.

(more…)

04/25/14 5:15pm
04/25/2014 5:15 PM
The site of construction at Costco in late March. (Credit: Tim Gannon)

The site of construction at Costco in late March. (Credit: Tim Gannon)

The controversial Costco/Shops at Riverhead development on Route 58 has been issued a stop work order, putting the entire project on hold until the developer can show that the work being done is in conformance with its approved site plan, according to Riverhead Town Attorney Bob Kozakiewicz.  (more…)