News

Town settles dump lawsuit; piles $200k more on debt mountain

BARBARAELLEN KOCH PHOTO
Riverhead Town has reached a settlement with a contractor over work on capping the town landfill, which will soon be opened to the public for activities such as hiking and biking.

Riverhead Town will pay $192,000 more to Terry Contracting under the terms of a settlement that will end a legal dispute over costs associated with the town’s newly completed landfill capping project.

The town bonded $10 million in January 2008 to cap the fill still left there after an attempt at reclaiming the dump property — a process that involves removing garbage and recyclables — went way over budget. The town spent $41 million on reclamation and completed only about one-third of the job, according to officials.

Terry Contracting, a Riverhead firm, was awarded the capping contract after submitting a $7.4 million bid, which was much lower than any of the others. The $10 million bond also included money for construction management as well as for contingency funds, in case the project cost more than expected, which officials initially said was possible given that some of the landfill had spilled onto neighboring property.

Town officials said last year that the final capping price was $8.2 million.

The dispute with Terry Contracting involved a disagreement over which section of the contract some work fell under, according to Riverhead Supervisor Sean Walter.

“There was no way of knowing the extent of the garbage, because it went off onto other people’s property,” Mr. Walter said. “Terry Contracting went and removed it from the other people’s property, and put it on top of the landfill. He was to be paid for a certain height of the landfill, but all the extra garbage required him to go over that height, so there was a dispute.”

Mr. Walter said Terry was seeking about $350,000.

“The attorneys discussed it and came to a resolution that, since nobody knew the scope of where the garbage went and nobody knew the height of the cap was going to be changed because we didn’t know [how much] garbage was on other people’s property, we didn’t want to get into a long protracted litigation so we kind of split the difference.”

The cost still comes under the $10 million that was bonded for the capping, Mr. Walter said.

“He’s done a good job,” Councilman John Dunleavy said of Terry Contracting.

Representatives of Terry Contracting could not be reached for comment, although their attorney has signed the settlement. The Town Board was expected to approve the settlement agreement at its Wednesday-afternoon meeting.

[email protected]

Looking to comment on this article? Send us a letter to the editor instead.